Decision Maker: Cabinet
Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: No
To consider a report on the partnership approach and procurement strategy for the Smart, Sponge Catchments Project which is a capital grant funded flood resilience project.
(a) Enter into the grant agreements with Wildfowl & Wetlands Trust (WWT) and National Flood Forum (NFF);
(b) Approve extensions and variations to the grant agreements to WWT and NFF, subject to available grant funding, for the life of the project through to April 2027, encompassing extensions for 2023/24, 2024/25, 2025/26 and 2026/7 financial years.
(a) Approve the procurement and award of contract of technical consultancy services to complete hydraulic modelling of options, assessments, and conceptual design to an expected maximum value of £106,000;
(b) Approve the procurement and award of contract of technical consultancy services to inform and prepare the Full Business Case to an expected maximum value of £455,000;
(c) Approve the procurement and award of contract of smart technology services to inform the Full Business Case, including the proof of concept, sensor trials and development of a data sharing platform, to an expected maximum value of £92,800; and
(d) Approve the procurement of smart technology services to operate and evaluate sensor monitoring and the data platform to an expected maximum value of £511,500 to cover the period to 31st March 2027 and to note that the Executive Director will report to Cabinet for recommendation of award of contract where the contract value exceeds £500,000.
4. Approved the Executive Director - Place and Communities as project sponsor and delegate responsibility to maintain and update the Governance Strategy for the project.
Publication date: 25/11/2022
Date of decision: 21/11/2022
Decided at meeting: 21/11/2022 - Cabinet